The Rapu-Rapu Polymetallic Project (RRPP) is the first mine set up in the Philippines after RA 7942 or the Philippine Mining Act of 1995 took effect.  The mine produces copper and zinc concentrates, with gold and silver by-products, making the pioneer polymetallic mine established under the new mining law.

RRPP is the largest private enterprise in Albay, with investments of over US$100 million.  Together with its contractors, the mine employs over 1,400 persons, of whom ninety percent come from the Bicol region.

The Project is jointly operated by the Rapu-Rapu Minerals, Inc. (RRMI) and the Rapu-Rapu Processing, Inc. (RRPI).  In October 2008, three shareholders, LG International (LGI), Korea Resources Corp. (KORES), and Malaysia Smelting Corp. (MSC) invested in RRPP and restarted its operations; guided by commitments to responsible mining for sustainable development, to respect the interest of all stakeholders, and to develop partnerships to realize socio-economic progress for the country.

  • First mining project to operate after the 1995 Philippine Mining Act
  • Located in the easternmost tip of Rapu-Rapu Island, Rapu-Rapu,
    Albay, Bicol Region.
  • Largest private venture in Albay at US$100M investment.
  • Employs 80% of manpower from Bicol
  • ISO 14001:2004 certified EMS for RRPI and RRMI
  • Awarded safest mining operation in the Philippines for 2010
  • PhP830M total tax remittances as of September 2010
  • Only mine in the Philippines to support FMRDP prior to approval

History Highlights

December 1999 Acquired 100% interest in the Ungay-Malobago mine
October 2000 Environmental Impact Assessment was finalized
January 2001 Feasibility Study was completed
July 2001 DENR granted an ECC
April 2002 DENR approved EPEP
June-October 2005 Gold plant operation
Oct 05 to Jun 06 Rehabilitation of mine facilities
Jun 06 to Feb 07 Test run of base metal flotation plant
February 2007 Start of commercial operation
January 2008 Cessation of operation due to financial constraints
April 2008 Acquisition of RRPP by LG International, Korea Resources Corp., and Malaysia Smelting Corp.
October 2008 Resumed commercial operation
July 2010 Finished plant upgrade by addition of 6 flotation cells